Saturday, March 14, 2020


Actual date posted: Monday 08 February 2021 

Short video showing the position of the building block, facing South looking onto Road 2334.

Originally added 327 loads of poor quality soil to raise the level of the block we will be building on.

A further 512 loads were added to several surrounding rice fields to make the overall level of the site more suitable, particularly for the rainy season.  Cost was THB 190 per load including tractor hire.

No comments:

Post a Comment

 NEW SHED Actual date of post: 13 February 2021 Work commenced Thursday 11/02/21 on construction of a new storage shed, replacing the old di...